Williamsport levee project completes eight pump station roofs

SEDA-COG said Williamsport’s approximately $10.7 million levee project has completed roof replacements at all eight pump stations and will continue through April 30, 2028.

By Williamsport Local Staff
Ask AI

Summarize this page with

ChatGPTClaudePerplexityGoogle AI
Editorial illustration: Williamsport levee project completes eight pump station roofs

In short

  • Williamsport’s levee upgrade project has completed roof replacements at all eight pump stations and is advancing electrical and relief-well work, S...
  • The approximately $10.7 million FY2023 Legislative Pre-Disaster Mitigation project was discussed at a Williamsport City Council meeting on Nov. 5, ...
  • Weatherproofing Technologies Inc., working through the Keystone Purchasing Network, completed the roofs, while additional stabilization work is und...

Williamsport’s levee upgrade project has completed roof replacements at all eight pump stations and is advancing electrical and relief-well work, SEDA-Council of Governments (SEDA-COG) announced Nov. 9. The approximately $10.7 million FY2023 Legislative Pre-Disaster Mitigation project was discussed at a Williamsport City Council meeting on Nov. 5, according to the announcement.

Weatherproofing Technologies Inc., working through the Keystone Purchasing Network, completed the roofs, while additional stabilization work is underway, SEDA-COG said. Electrical improvements at the City’s levee pump stations are also moving forward: after City Council approved the construction contract in August 2026, Lecce Electric began coordinating implementation with Greenman-Pedersen Inc., the City’s construction management and inspection consultant, according to the announcement.

SEDA-COG said AECOM submitted a proposed scope for the next phase of relief-well engineering, dated Oct. 13, 2026. The proposal includes about 25 geotechnical borings, 10 test and pumping wells, pumping tests, seepage and stability analyses, and plans, specifications and construction cost estimates, the announcement said. The engineering approach has been submitted to the U.S. Army Corps of Engineers for review and concurrence, SEDA-COG said.

About $1.75 million in Pennsylvania Redevelopment Assistance Capital Program funding has been identified for relief-well construction, according to SEDA-COG. The City’s federal grant period has been extended through April 30, 2028, giving the project more time for remaining construction and engineering, the announcement said.

SEDA-COG said it serves as the City’s grant administrator and will continue coordinating the work, including pump-station electrical improvements, remaining stabilization and the relief-well engineering process.

Know someone who should see this?

Ask AI

Summarize this page with

ChatGPTClaudePerplexityGoogle AI

Also in Williamsport

Your town, every weekday morning

What’s on today, new local guides and stories, in one short free email.

Free. Unsubscribe any time.